COST OF THE PROJECT
- CONSTRUCTION COST WITH FEES 158.12 CR
- APPROVALS AND ALL PREMIUMS 165.21 CR
- EXPENSES FOR TENANTS 67.52 CR
- TOTAL COST 390.85 CR
- INTEREST 43.97 CR
- INFLATION 19.54 CR
- MARKETING N SELLING EXPENSES 18.13 CR
- TOTAL COST WITH INTEREST 472.49 CR
REVENUE OF PROJECT - REVENUE OF PROJECT 614.35 CR
- TOTAL COST OF PROJECT 472.49 CR
- PROFIT OF PROJECT (30 % of Project Cost) 141.86 CR